Work
CASE STUDY:
Northeast Utilities: Long Mountain Substation
Facts:
Type: Substation
Date: Completed 2008
Description:
BOND excavated and removed twelve existing breaker foundations and installed twelve new 20,000 pound precast foundations inside the 550 kV Long Mountain Substation for SM Electric. All work occurred on a fast track schedule during two separate shutdowns to maximize the use of the substation during construction. The foundations support 12 state-of-the-art Siemens 550 kV dead tank circuit breakers. The breakers are the first of their kind in the United States and have a higher load capacity, require less maintenance and are faster and more dependable than traditional breakers, increasing the reliability of the electrical grid.
Challenge/Situation:
Working in a live high voltage electrical substation with low overhead clearance and very limited maneuverability within an existing substation infrastructure during difficult weather conditions posed a challenge.
Solution/Action:
Since the use of conventional methods of placing concrete was not practical in this situation the decision was made to carefully survey, layout, excavate and install precast systems.
Benefit/Result:
By using the precast foundation system, the potential for service interruption was mitigated.
Type: Substation
Date: Completed 2008
Description:
BOND excavated and removed twelve existing breaker foundations and installed twelve new 20,000 pound precast foundations inside the 550 kV Long Mountain Substation for SM Electric. All work occurred on a fast track schedule during two separate shutdowns to maximize the use of the substation during construction. The foundations support 12 state-of-the-art Siemens 550 kV dead tank circuit breakers. The breakers are the first of their kind in the United States and have a higher load capacity, require less maintenance and are faster and more dependable than traditional breakers, increasing the reliability of the electrical grid.
Challenge/Situation:
Working in a live high voltage electrical substation with low overhead clearance and very limited maneuverability within an existing substation infrastructure during difficult weather conditions posed a challenge.
Solution/Action:
Since the use of conventional methods of placing concrete was not practical in this situation the decision was made to carefully survey, layout, excavate and install precast systems.
Benefit/Result:
By using the precast foundation system, the potential for service interruption was mitigated.
Case Studies
- Long Mountain Substation
- Northeast Utilities
- Braintree Electric Light Department, Watson Station
- O&G Industries
- Allston Development Group
- Harvard University
- Metrowest Water Supply Tunnel
- MWRA
- Boston Street Furniture Program
- Wall USA
- Long Mountain Substation
- Northeast Utilities
- Memorial Drive 115kV Electrical Duct Bank
- NSTAR
- Middletown/Norwalk 345 kV Transmission Line
- Northeast Utilities
- Underground Shafts at 165 Tremont Street
- Tishman Construction
- Utility Upgrade
- Brown University
- Gas Line Installation
- Spectra Energy
