CASE STUDY:
O&G Industries: Braintree Electric Light Department, Watson Station
Facts:
Type: Civil/Concrete
Date: Completed 2009
Description:
BOND undertook heavy civil and concrete work in support of construction of a new power plant. BOND played a significant role as part of the design/build team to provide mass excavation, sitework, underground utilities, and cast-in-place concrete, as well as managing the installation of interior finishes of the control room for this new waterfront power plant in Braintree, MA. Our crews formed and placed over 4,000 cubic yards of structural concrete, and installed a steel sheet earth support system serving as a seawall along the waterway. The site safety plan and environmental controls required great diligence.
Challenge/Situation:
The project needed to meet an accelerated construction schedule and quick delivery of mechanical towers.
Solution/Action:
Customized anchor bolt placement templates were employed as part of our quality control program.
Benefit/Result:
The anchor bolt installation enabled electrical and mechanical contractors to set equipment without difficulty or delay, and without impact to the strength of the bolt or concrete.
Type: Civil/Concrete
Date: Completed 2009
Description:
BOND undertook heavy civil and concrete work in support of construction of a new power plant. BOND played a significant role as part of the design/build team to provide mass excavation, sitework, underground utilities, and cast-in-place concrete, as well as managing the installation of interior finishes of the control room for this new waterfront power plant in Braintree, MA. Our crews formed and placed over 4,000 cubic yards of structural concrete, and installed a steel sheet earth support system serving as a seawall along the waterway. The site safety plan and environmental controls required great diligence.
Challenge/Situation:
The project needed to meet an accelerated construction schedule and quick delivery of mechanical towers.
Solution/Action:
Customized anchor bolt placement templates were employed as part of our quality control program.
Benefit/Result:
The anchor bolt installation enabled electrical and mechanical contractors to set equipment without difficulty or delay, and without impact to the strength of the bolt or concrete.
Case Studies
- Braintree Electric Light Department, Watson Station
- O&G Industries
- Braintree Electric Light Department, Watson Station
- O&G Industries
- Allston Development Group
- Harvard University
- Metrowest Water Supply Tunnel
- MWRA
- Boston Street Furniture Program
- Wall USA
- Long Mountain Substation
- Northeast Utilities
- Memorial Drive 115kV Electrical Duct Bank
- NSTAR
- Middletown/Norwalk 345 kV Transmission Line
- Northeast Utilities
- Underground Shafts at 165 Tremont Street
- Tishman Construction
- Utility Upgrade
- Brown University
- Gas Line Installation
- Spectra Energy